Timeline & Next Steps
Timeline & Next Steps
This is an outline of the key milestones for the project.
2026
- March-May: Public consultation (you are here)
- June-July: Analysis of feedback and design refinement
- September: Publication of consultation report
- November: Outline planning application submitted
2027
- Q1: Planning determination expected
- Q2: Detailed design phase begins
- Q4: Phase 1 construction starts (Market Square & High Street north)
2028-2030
- Phased delivery of remaining character areas
- Ongoing community engagement throughout construction
How your feedback will be used
All responses will be analysed and a summary report published. Your feedback will directly inform the detailed design and planning application.